Construction Continues On Columbus Road

By:
Posted on:

< < Back to construction-continues-columbus-road

York Paving is expected to continue Columbus Road work the week of Sept. 30. Activities will include installing the curb along the medians and completing an asphalt leveling course on Columbus Road. Both activities are expected to begin on Monday. Traffic will be maintained on Columbus Road during these activities, but flaggers will be present.

York Paving will also be working on North Lancaster Street water service installation. During service line installation North Lancaster Street may be reduced to one-lane adjacent to the work zone and two-way traffic will be maintained by flagging.

 

The city of Athens apologizes for any inconvenience that may be incurred during this work. Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 593-7636.