Concerns about cultural sites lead to the downsizing of proposed locations for a Pike County data center complex
By: David Forster
Posted on:
ATHENS, Ohio (WOUB) — The company planning to build a massive data center complex in Pike County has reduced the size of the proposed project area by half in its permit application.
At least some of this has to do with concerns over sensitive cultural sites.
SB Energy initially was planning to build the data centers on more than 1,000 acres of private property just south of Piketon.
But according to its latest filings with the Ohio Environmental Protection Agency, it is now looking to build on less than 500 acres.

The plant, located a couple of miles south of Piketon, enriched uranium for the U.S. military and commercial nuclear reactors for decades and is now undergoing an extensive cleanup of radioactive and other contamination.
But since that March announcement, SB Energy has been pursuing the necessary state and federal permits to build what was identified in its original permit application as a 10 gigawatt data center complex on several large parcels of private land outside the plant site.
These permits include permission from the state and the federal government to fill in or otherwise disturb streams and wetlands.
In late September, the federal Permitting Council issued a document noting that a permit from the U.S. Army Corps of Engineers would be delayed because SB Energy had made “a significant change to the extent of the project area to avoid a cultural site.”
These changes, according to the document, “had the benefit of significantly reducing impact to sensitive cultural resources and other areas.”
WOUB reached out to SB Energy and the Army Corps of Engineers to find out the nature of these cultural sites and the concerns they raised.
In a reply, SB Energy did not address the cultural sites but said: “There were multiple reasons why we removed those parcels, including contiguity with the rest of the development.”
The Army Corps of Engineers’ office for the district that includes southeast Ohio did not respond to emails and a voicemail message.
SB Energy says it still plans to build a 10 gigawatt data center complex in Pike County, but it’s unclear at this point how much of that will be built on the remaining acreage from its original permit application.
“Not all projects are in this permit application,” the company said in an email. “The plan continues to be for a 10 GW data center complex, comprised of multiple standalone projects.”
A spokesperson for SB Energy said in an email that grading work is beginning on a limited area that does not involve disturbing waterways and for which the company already has the necessary permits.
Construction of the first 800 megawatt project phase is expected to begin before the end of the year, the spokesperson said, “with capacity expected to come online in phases beginning in 2028.”